Answer: (A) 600 J
Concept: Work is done when a force moves a body. If a force F displaces a body through a distance S, and θ is the angle between the force and the displacement, the work done is W = FS cos θ. Work is a scalar, and its S.I. unit is the joule (1 J = 1 N × 1 m).
Step 1 — Find the angle between force and displacement.
The 200 N force acts along the slope, and the block moves along the slope from A to B. So θ = 0° and cos θ = 1.
Step 2 — Read the displacement from the figure.
The block moves the length of the slope, AB = 3 m.
Step 3 — Work out the work.
Multiply the force by the displacement along it.
W=F×S=200 N×3 m=600 J

Step 4 — See why the height is not used.
The height BC (1·5 m) would be needed only for the work done against gravity. Taking g = 10 m s⁻², that part is
mgh=20×10×1.5=300 J
Since the block moves at constant speed, the other 300 J of the force's work is spent against friction.
Watch out: Use the distance moved ALONG the force (3 m), not the vertical height (1·5 m).
Why the other options are wrong:
- (B) 500 J: no correct use of the data gives 500 J: F × AB is 600 J, and even the gain in potential energy is only 300 J.
- (C) 60 J: 60 J multiplies the mass 20 kg by 3 m, using a mass in place of a force in newton.
- (D) 200 J: 200 J is the work over only 1 m of the slope, not the full 3 m.
Therefore, the work done in moving the block from A to B is 600 J, option (A).