A and B together can do a piece of work in 6 days. Whereas A alone can do the same work in 9 days. Then B alone will do same work in:
Solving (simple) Problems · Question 31 of 88
A and B together can do a piece of work in 6 days.
(A) 15 days
(B) 6 days
- Correct answer
(C) 18 days
(D) 54 days
Answer: (C) 18 days
Concept: If someone can finish a work in days, he does of the work in one day. When people work together, their one-day works add up, and the time taken together is 1 divided by the total one-day work.
Step 1 — Write the one-day works.
A and B together finish the work in 6 days, so together they do of it in one day. A alone takes 9 days, so A does of it in one day.
Step 2 — Find B's one-day work.
B's one-day work is the joint one-day work minus A's one-day work. We use the L.C.M. 18.
Step 3 — Find B's time.
B does of the work in one day, so B needs 18 days to finish it alone.
Watch out: Subtract the one-day works (), never the days (9 − 6).
Why the other options are wrong:
- (A) 15 days: this adds the days, 6 + 9. Days do not add; one-day works do.
- (B) 6 days: 6 days is the time for A and B together; B alone must take longer than that.
- (D) 54 days: this multiplies the days, 6 × 9. B's one-day work is 1/18, so B needs 18 days.
Therefore, B alone will do the work in 18 days, option (C).