Competency-Based Questions (CBQ) · Question 9 of 40

Competency: Analysis & Evaluation A company wants to set up a wind farm and has collected the following data for three…

Question 92 marksMedium

Competency: Analysis & Evaluation

A company wants to set up a wind farm and has collected the following data for three sites.

SiteAverage speed of windHow the wind blows
P12 km h−1^{-1}steadily throughout the year
Q20 km h−1^{-1}steadily throughout the year
R40 km h−1^{-1}for about two months of the year; almost still in the other months

(a) Which site should the company choose ? Give the reason for rejecting each of the other two.

(b) State one more thing about the chosen site that the company must check before building the wind farm.