Competency-Based Questions (CBQ) · Question 17 of 40

Competency: Application A city bus depot plans how many AC buses ( x ) and non-AC buses ( y ) to run on a busy route…

Question 173 marksMedium

Competency: Application

A city bus depot plans how many AC buses (xx) and non-AC buses (yy) to run on a busy route in the morning peak. An AC bus has 40 seats and a non-AC bus 50 seats, and at least 1,200 seats are needed in the peak. To keep the gap between buses short, at least 26 buses must run, and at least 6 of them must be AC buses. Running an AC bus in the peak costs ₹ 3,000 and a non-AC bus ₹ 2,000. The depot has enough buses of both kinds. (Hypothetical data.)

(a) Write the objective function and the constraints.

(b) Find the corner points of the feasible region and the plan with the least cost.

(c) The feasible region is unbounded. Show that the least corner value found in (b) is really the minimum cost.