Competency-Based Questions (CBQ) · Question 23 of 44

Competency: Application A tower crane on a building site has a horizontal jib on a vertical tower, as shown.

Question 234 marksHard

Competency: Application

A tower crane on a building site has a horizontal jib on a vertical tower, as shown. On one side of the tower axis, a counterweight of 16 t16\ \text{t} hangs 12 m12\ \text{m} from the axis, and the counter-jib that carries it has a mass of 4 t4\ \text{t} acting 6 m6\ \text{m} from the axis. On the other side, the main jib has a mass of 8 t8\ \text{t} acting 20 m20\ \text{m} from the axis, and a load hangs from a trolley that can run along the jib. For safety, the total moment of all these weights about the tower axis, in either direction, must never be more than 784 kN m784\ \text{kN m}; the tower and its base supply the rest. (Hypothetical data.) Take g=9.8 m s−2g = 9.8\ \text{m s}^{-2} and 1 t=1000 kg1\ \text{t} = 1000\ \text{kg}.

Class 11 Physics Newton's Laws of Motion Question 23

(a) With no load on the hook, find the total moment of the weights about the tower axis, and say which way it tends to turn the top of the tower. Is the crane safe?

(b) Find the largest load that may be lifted with the trolley (i) 40 m40\ \text{m} and (ii) 20 m20\ \text{m} from the axis.

(c) The site manager suggests adding 3 t3\ \text{t} to the counterweight so that heavier loads can be lifted at 40 m40\ \text{m}. Show, with a calculation, why this is not allowed.