Previous Year Questions · Question 4 of 23

In an automobile factory, certain parts are to be fixed into the chassis in a section before it moves into another…

Question 45 marksAsked 2016Medium

In an automobile factory, certain parts are to be fixed into the chassis in a section before it moves into another section. On a given day, one of the three persons A, B and C carries out this task. A has 45% chance, B has 35% chance and C has 20% chance of doing the task. The probability that A, B and C will take more than the allotted time is 16,110\dfrac{1}{6}, \dfrac{1}{10} and 120\dfrac{1}{20} respectively. If it is found that the time taken is more than the allotted time, what is the probability that A has done the task?