In an automobile factory, certain parts are to be fixed into the chassis in a section before it moves into another section. On a given day, one of the three persons A, B and C carries out this task. A has 45% chance, B has 35% chance and C has 20% chance of doing the task. The probability that A, B and C will take more than the allotted time is and respectively. If it is found that the time taken is more than the allotted time, what is the probability that A has done the task?
Previous Year Questions · Question 4 of 23
In an automobile factory, certain parts are to be fixed into the chassis in a section before it moves into another…
Solution:
Key idea: We know the result (the time was exceeded) and want the chance of one cause (A did the task). Bayes' theorem gives .
Step 1 — Write the given probabilities.
Let , , also denote the events that A, B, C does the task, and the event that the time taken is more than allotted.
Step 2 — Find each person's share of the delay.
We multiply each person's chance of doing the task by their chance of taking too long.
Step 3 — Find the total probability of a delay.
The three cases cover every possibility, so we add them.
Step 4 — Apply Bayes' theorem.
We divide A's share by the total.
Therefore, the probability that A did the task, given that the time was exceeded, is .