Practice Questions · Question 28 of 40

Bloom's level: Evaluate 20 workers can finish a road in 9 days.

Question 284 marksMedium

Bloom's level: Evaluate

20 workers can finish a road in 9 days. Raju works out how long 30 workers will take:

"20 workers take 9 days, so 1 worker takes 9÷209 \div 20 days, and 30 workers take 9÷20×30=13129 \div 20 \times 30 = 13\frac{1}{2} days."

(a) Without calculating, is Raju's answer sensible? Explain.

(b) What mistake did Raju make?

(c) Find the correct answer.