Question 222 marksMedium
Bloom's level: Analyse
The table shows how many days different numbers of workers take to build the same shed.
| Workers | 2 | 4 | 6 | 12 |
|---|---|---|---|---|
| Days | 30 | 15 | 10 | ? |
(a) Multiply workers × days for the first three columns. What do you notice?
(b) Use this to find the missing number of days.