Bloom's level: Apply A contractor planned to dig a village pond with 14 workers, and they would need 15 days.

Question 202 marksEasy

Bloom's level: Apply

A contractor planned to dig a village pond with 14 workers, and they would need 15 days. He then got 21 workers instead. Now in how many days will the pond be ready?