Practice Questions · Question 26 of 40

Bloom's level: Analyse Case study: Ramesh and Suresh are painting their school's boundary wall.

Question 265 marksMedium

Bloom's level: Analyse

Case study: Ramesh and Suresh are painting their school's boundary wall. Working alone, Suresh would take 6 days more than Ramesh. Working together, they finish the job in 4 days.

(a) If Ramesh alone takes xx days, write the part of the wall each of them paints in one day.

(b) Form a quadratic equation and find how long each would take alone.

(c) On another identical wall they work together for 2 days, after which Ramesh leaves. How many more days will Suresh need to finish the wall alone?