Question 192 marksEasy
If 5 workers can complete a task in 8 days, how many workers are needed to complete the same task in 4 days?
Confirming your payment
Practice Questions · Question 19 of 35
If 5 workers can complete a task in 8 days, how many workers are needed to complete the same task in 4 days?
Sol.
Let the number of workers required be .
| Number of Workers | 5 | |
|---|---|---|
| Number of Days | 8 | 4 |
Since the task completion time decreases as the number of workers increases, this is a case of inverse proportion.