Three workers can paint a fence in 4 days. If one more worker joins the team, how many days will it take them to finish the work? What are the assumptions you need to make?
Confirming your payment
Proportional Reasoning–2 · Question 16 of 22
Three workers can paint a fence in 4 days. If one more worker joins the team, how many days will it take them to finish the work? What are the assumptions you need to make?
The number of workers and the number of days are in inverse proportion.
Assumptions:
(i) All workers work at the same rate.
(ii) They work for the same number of hours each day.
(iii) Total work remains fixed.
Let the number of days be .
Therefore, they will take 3 days to finish the work.