22 men can dig a 27 m long trench in one day. How many men should be employed for digging 135 m long trench of the same type in one day ?
Direct and Inverse Variations · Question 13 of 63
22 men can dig a 27 m long trench in one day.
Solution:
Concept: Two quantities vary directly when they increase (or decrease) together in the same ratio. Then the quotient is the same for every pair of values; this fixed number is the constant of variation, and .
Given: 22 men dig a 27 m trench in one day.
Step 1 — Decide the type of variation.
The time is fixed at one day. A longer trench needs more men, in the same ratio, so the number of men varies directly with the length of the trench.
Step 2 — Compare the two lengths.
We divide the new length by the old length to see how many times longer the new trench is.
So the new trench is 5 times as long.
Step 3 — Find the number of men.
Five times the length needs five times the men in the same one day.
Watch out: The time stays one day, so this is direct variation; more work in the same time needs more men.
Therefore, 110 men should be employed.