A can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
Direct and Inverse Variations · Question 39 of 63
A can do a piece of work in 20 days and B in 15 days.
Solution:
Concept: If someone can finish a whole piece of work in days, then in ONE day they do of it. When people work together, their one day's works add up. The whole work is taken as 1, and time needed work to be done one day's work.
Given: A alone takes 20 days, B alone 15 days; they work together for 6 days, then A leaves.
Step 1 — Find the joint one day's work.
A does of the work in a day and B . We add them with the common denominator 60.
Step 2 — Find the work done in 6 days.
They work together for 6 days.
Step 3 — Find the work left.
We subtract the work done from the whole work.
Step 4 — Find B's time for the rest.
B alone finishes the rest at of the work per day, so we divide the work left by B's one day's work.
So B needs more days.
Watch out: After A leaves, divide by B's one day's work only, not by the joint one day's work.
Therefore, B will take days to finish the remaining work.