A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?
Direct and Inverse Variations · Question 59 of 63
A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days.
Solution:
Concept: If someone can finish a whole piece of work in days, then in ONE day they do of it. When people work together, their one day's works add up. The whole work is taken as 1, and time needed work to be done one day's work.
Given: A and B take 8 days, B and C 12 days, and A and C 16 days.
Step 1 — Add the three pairs.
A and B do of the work in a day, B and C , and A and C . Adding the three pairs counts each person twice. The L.C.M. of 8, 12 and 16 is 48.
Step 2 — Find the one day's work of all three.
We halve the sum, because each person was counted twice.
Step 3 — Find the time together.
Time needed is the whole work divided by the one day's work.
As a mixed number this is days.
Watch out: Remember to halve the sum of the three pairs; without halving you would get the time for “two teams” of A, B and C.
Therefore, all three working together can do the work in days.