Solution:
Concept: For a fixed job (or a fixed amount of food, a fixed distance), the number of men (pipes, students, km per hour) and the time taken vary inversely: their product stays the same.
Given: 72 men do the work in 25 days.
Step 1 — Decide the type of variation.
The work is fixed. Fewer men take more days, so men and days vary inversely: men × days stays the same.
Step 2 — Find the days for 30 men.
We divide by 30.
Therefore, 30 men will do the same work in 60 days.