A can do of a work in 5 days and B can do of the same work in 10 days. Find the number of days in which both working together will complete the work.
Direct and Inverse Variations · Question 42 of 63
A can do 1/4 of a work in 5 days and B can do 1/3 of the same work in 10 days.
Solution:
Concept: If someone can finish a whole piece of work in days, then in ONE day they do of it. When people work together, their one day's works add up. The whole work is taken as 1, and time needed work to be done one day's work.
Given: A does of the work in 5 days; B does of it in 10 days.
Step 1 — Find A's time for the whole work.
A does of the work in 5 days, so the whole work (4 quarters) takes 4 times as long.
Step 2 — Find B's time for the whole work.
B does of the work in 10 days, so the whole work (3 thirds) takes 3 times as long.
Step 3 — Find the joint one day's work.
Now A does and B of the work in a day. We add them with the common denominator 60.
Step 4 — Find the time together.
Time needed is the whole work divided by the one day's work.
Watch out: 5 days is the time for only a quarter of the work; A's one day's work is , not .
Therefore, working together, A and B complete the work in 12 days.