Direct and Inverse Variations · Question 62 of 63

A can do a piece of work in 10 days, B in 12 days and C in 15 days.

Question 623 marksMedium

A can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished. How long did the work last ?

Suppose the work lasts for xx days.

∴\therefore A worked for 2 days, B for (x−3)(x - 3) days and C for xx days.

⇒\Rightarrow A's 2 days work + B's (x−3)(x - 3) days work + C's xx days work = 1

⇒2×110+(x−3)×112+x×115=1\Rightarrow 2 \times \dfrac{1}{10} + (x - 3) \times \dfrac{1}{12} + x \times \dfrac{1}{15} = 1