Statement 1 : Work done varies inversely to the number of persons at work.
Statement 2 : Time taken to finish a work varies directly to the number of persons at work.
Which of the following options is correct?
Confirming your payment
Sign up now and get 250 free tokens.
Direct and Inverse Variations · Question 49 of 63
Statement 1 : Work done varies inversely to the number of persons at work.
Statement 2 : Time taken to finish a work varies directly to the number of persons at work.
Which of the following options is correct?
(A) Both the statements are true.
(B) Both the statements are false.
(C) Statement 1 is true, and statement 2 is false.
(D) Statement 1 is false, and statement 2 is true.
Answer: (B) Both the statements are false.
Concept: Work done in a fixed time varies directly with the number of workers, and the time taken for a fixed job varies inversely with the number of workers.
Step 1 — Judge Statement 1.
In a given time, more persons do MORE work. So work done varies directly with the number of persons, not inversely. Statement 1 is false.
Step 2 — Judge Statement 2.
For a given piece of work, more persons finish it in LESS time. So the time taken varies inversely with the number of persons, not directly. Statement 2 is false.
Watch out: The two statements swap the words “directly” and “inversely”; read which quantity is kept fixed.
Why the other options are wrong:
Therefore, both statements are false, option (B).