12 men can make a certain number of screws in 30 days. The number of screws, of the same type will be made by 24 men in :
Direct and Inverse Variations · Question 17 of 63
12 men can make a certain number of screws in 30 days.
- Correct answer
(A) 15 days
(B) 30 days
(C) 60 days
(D) none of these
Answer: (A) 15 days
Concept: For a fixed job (or a fixed amount of food, a fixed distance), the number of men (pipes, students, km per hour) and the time taken vary inversely: their product stays the same.
Step 1 — Decide the type of variation.
The number of screws is fixed. More men finish it in fewer days, so men and days vary inversely: men × days stays the same.
Step 2 — Find the constant product.
We multiply the men by the days for the given case.
Step 3 — Find the days for 24 men.
We divide the constant product by 24.
Watch out: Doubling the men halves the days; it does not double them.
Why the other options are wrong:
- (B) 30 days: 30 days is the time for 12 men; it ignores the extra 12 men.
- (C) 60 days: 60 days is , which treats men and days as direct variation.
- (D) none of these: “none of these” is wrong because the correct value, 15 days, is option (A).
Therefore, 24 men make the screws in 15 days, option (A).