Solution:
Concept: If a person can finish a work in n days, he does n1 of it in 1 day (his one day's work). People working together add their one day's works, and the time for the whole work is 1÷(one day’s work).
Step 1 — Part (i).
A does 31 of the work in 10 hours, so in 1 hour he does one-tenth of that.
A’s 1 hour’s work=31÷10=31×101=301
Step 2 — Part (ii).
B does 52 of the work in 12 hours, so in 1 hour he does one-twelfth of that.
B’s 1 hour’s work=52÷12=52×121=602=301
Step 3 — Part (iii).
Working together, they add their one hour's works.
Together in 1 hour=301+301=302=151
They do one-fifteenth of the work each hour, so the whole work takes 15 hours.
Time together=1÷151=15 hours
Watch out: A does only 31 of the work in 10 hours, so his whole-work time is 30 hours, not 10.
Therefore, (i) A does 301 of the work in 1 hour; (ii) B also does 301 in 1 hour; (iii) working together they complete the work in 15 hrs.