Unitary Method · Question 48 of 58

20 workers complete a certain piece of work in 28 days.

Question 481 markMCQEasy

20 workers complete a certain piece of work in 28 days. The number of days required to complete half of this work by 8 workers is :

Select your answer
  • (A) 35

    Correct answer
  • (B) 70

  • (C) 105

  • (D) 140