A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in : (i) one day (ii) 2 days.
What part of work will be left, after they have worked together for 2 days ?
Confirming your payment
Sign up now and get 250 free tokens.
Unitary Method · Question 35 of 58
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in : (i) one day (ii) 2 days.
What part of work will be left, after they have worked together for 2 days ?
Solution:
Concept: We count the whole work as 1. If a person finishes it in days, his one day's work is ; the work done in some days is (one day's work) × (number of days), and the work left is 1 minus the work done.
Step 1 — Part (i).
A does of the work in a day and B does . Together they do the sum. The L.C.M. of 4 and 5 is 20.
Step 2 — Part (ii).
In 2 days they do twice the work of one day.
Step 3 — Find the work left.
The whole work is 1, so the part left is 1 minus the work done.
Therefore, (i) they do of the work in one day; (ii) in 2 days; and of the work is left after 2 days.