12 men take 18 days to construct a road. Find the number of days 9 men take to construct the same road.
Unitary Method · Question 15 of 24
12 men take 18 days to construct a road. Find the number of days 9 men take to construct the same road.
Solution:
Concept: Some quantities change in opposite ways (inverse changes). More workers finish a job in fewer days, and the same food lasts fewer days for more people. So we first find the answer for one by multiplying, and then divide by the new number.
Given: 12 men build the road in 18 days.
Step 1 — Find the days for 1 man.
1 man works alone, so he needs more time than 12 men: 12 times as many days. We multiply (more time, so multiply).
Step 2 — Find the days for 9 men.
9 men share the work, so they need less time than 1 man. We divide (less time, so divide).
Watch out: Fewer men (9 instead of 12) need more days, so the answer must be more than 18 days. 24 fits.
Therefore, 9 men will take 24 days to build the road.