112 men can build a railway tunnel in 72 days. How many more men will be required to build the tunnel in 48 days?
Unitary Method · Question 24 of 24
112 men can build a railway tunnel in 72 days. How many more men will be required to build the tunnel in 48 days?
Solution:
Concept: Some quantities change in opposite ways (inverse changes). More workers finish a job in fewer days, and the same food lasts fewer days for more people. So we first find the answer for one by multiplying, and then divide by the new number.
Given: 112 men build the tunnel in 72 days.
Step 1 — Find the men for 1 day.
To build the tunnel in just 1 day, we need 72 times as many men. We multiply (less time, so more men).
Step 2 — Find the men for 48 days.
48 days is more time than 1 day, so fewer men are needed. We divide.
Step 3 — Find how many more men.
The question asks how many MORE men are needed, so we subtract the 112 men already there.
Watch out: 168 is the total number of men needed. The answer is how many more: 168 − 112.
Therefore, 56 more men will be required to build the tunnel in 48 days.