Question 394 marksHard
Competency: Analysis & Evaluation
Case study: A school wants its stage painted. Ravi alone can do the job in 10 days and charges ₹ 500 for every day he works. Sana alone can do it in 15 days and charges ₹ 400 for every day she works. The principal thinks of three plans. Plan 1: Ravi alone. Plan 2: Sana alone. Plan 3: Ravi and Sana together. (Hypothetical data.)
(a) Find the number of days each plan takes.
(b) Find the total cost of each plan.
(c) The stage must be ready within 8 days. Which plan can the principal choose? How much more does it cost than the cheapest of the three plans?