Question 113 marksHard
Competency: Analysis & Evaluation
A contractor has to repair a road in 30 days. He puts 40 workers on the job. After 10 days he finds that only one-fourth of the road is repaired. All the workers work at the same rate.
(a) Is the work running on time? Give a reason.
(b) How many more workers must he put on the job to finish it in the 30 days?