Option (B) is correct.
Explanation:
The whole job is 16×15=240 worker-days of work (16 workers for 15 days).
In the first 5 days, 16 workers do 16×5=80 worker-days. Work left:
240−80=160
The work left is what 16 workers would do in the remaining 10 days. Now only 16−6=10 workers are left. Workers and days are inversely proportional, so
16×10=10×d,d=16 days
Total time =5+16=21 days.
Why the other options are wrong
- (A) 16 days is only the time after the change. The first 5 days must be added.
- (C) 24 days is the time if only 10 workers worked from the very start (240÷10). But 16 workers worked for the first 5 days.
- (D) 15 days ignores the change. With fewer workers for the rest of the job, it must take longer than 15 days.