A sweet shop in Varanasi has a big Diwali order of laddoos. From experience, the owner knows that 12 workers, all rolling at the same speed, finish such an order in 10 hours. The customer's van will come at a fixed time, and on festival days some workers have to leave early to reach home, so the owner cannot be sure who will stay. He is planning for three different situations, shown in the table.


(i) How long would 8 workers take for the whole order?
(ii) The 12 workers start the order, but after 4 hours, 3 of them go home. How many hours does the whole order take, from the start?
(iii) Instead, the owner wants the whole order ready 9 hours after the start. The 12 workers work for the first 4 hours. What is the least number of workers needed for the remaining time?