Competency-Based Questions (CBQ) · Question 38 of 40

At a village check dam near Ahmednagar, the store holds 30 bags of cement, 90 bags of sand and 180 bags of gravel.

Question 384 marksHard

At a village check dam near Ahmednagar, the store holds 30 bags of cement, 90 bags of sand and 180 bags of gravel. The engineer makes two concrete mixes, measured in bags: pillars use cement : sand : gravel =1:2:4= 1 : 2 : 4, and footings use 1:3:61 : 3 : 6. He first wants as much pillar mix as possible, and then plans to use whatever sand and gravel are left for the footings, buying extra cement from the town if needed.

Workers at a village check-dam site with cement bags, a sand heap, a gravel heap and a concrete mixer

Table of the store: cement 30 bags, sand 90 bags, gravel 180 bags; pillars 1 : 2 : 4, footings 1 : 3 : 6

(i) How many bags of cement, sand and gravel would 280 bags of pillar mix need?

(ii) Using only what is in the store, what is the largest amount of pillar mix that can be made? Which material runs out first?

(iii) All the sand and gravel left after (ii) are used for footing mix. How many bags of cement must be bought, and how many bags of footing mix will be made?