Competency-Based Questions (CBQ) · Question 18 of 40

The panchayat of a village near Satara is building a small check dam across a stream to store rainwater.

Question 184 marksMedium

The panchayat of a village near Satara is building a small check dam across a stream to store rainwater. The engineer uses two concrete mixes, measured in bags: the footings (the base under the wall) use cement : sand : gravel =1:3:6= 1 : 3 : 6, and the pillars use the stronger mix 1:2:41 : 2 : 4. Sand and gravel can be brought from the riverbank, but cement has to come from the town, and only 25 bags of cement are in stock today.

Workers at a village check-dam site with cement bags, a sand heap, a gravel heap and a concrete mixer

Table: footings use 1 : 3 : 6 and need 150 bags of mix; pillars use 1 : 2 : 4 and need 105 bags of mix; cement in stock 25 bags

(i) What fraction of the footing mix is cement?

(ii) How many bags of cement, sand and gravel are needed for the 150 bags of footing mix?

(iii) Is the cement in stock enough for both the footings and the pillars? If not, how many more bags of cement must be bought?